The following *schedule represents the typical “start-to-finish” process of a Lincoln/Lancaster County Habitat for Humanity construction project.
*All dates are tentative based on material availability and weather permitting.
|
Building System
|
Week Needed
|
Task
|
Workers Needed
|
Days Allotted
|
|
|
|
|
|
|
|
Excavation
|
Week # 1
|
|
|
|
|
Tentative start date:
|
Done
|
Excavate Foundation
|
Sub-contracted
|
1
|
|
|
February 22
|
Dig Footings
|
Sub-contracted
|
1-2
|
|
Foundation
|
February 23
|
Pour Footings
|
Sub-contracted
|
1
|
|
|
February 24
|
Pour Foundation
|
Sub-contracted
|
1
|
|
|
February 25
|
Frame walls/parts.
|
8-10
|
2
|
|
|
Week # 2
|
|
|
|
|
|
February 25
|
Trench/lay drain tile
|
8-12
|
1
|
|
|
|
Wall Coating
|
Sub-contracted
|
1
|
|
Temporary Power
|
Done
|
Set power pole
|
Sub-contracted
|
1
|
|
|
March 1
|
Backfill & Soak
|
N/A
|
1
|
|
Plumbing
Rough-in
|
March 1
|
Plumbing ground
Rough-in
|
Sub-contracted
|
2
|
|
Inspections
|
Week # 3
|
Inspect rough-in
|
N/A
|
1/2
|
|
Concrete Flatwork
|
March 6
|
Back-fill drains
|
6-8
|
1/2
|
|
|
March 6
|
Pour floor slab
|
Sub-contracted
|
1
|
|
|
|
Form/pour flatwork
|
Sub-contracted
|
2
|
|
Rough Framing
|
March 10
|
Frame floor deck
|
8-12
|
1/2
|
|
|
|
Subfloor
|
8-12
|
1/2
|
|
|
Week # 4
|
|
|
|
|
|
March 13 & 15
|
Frame basement
|
10-12
|
2
|
|
Wall Raising
|
Week # 5
|
|
|
|
|
|
March 24
|
Raise walls on site
|
15-20
|
1
|
|
|
|
Set roof trusses
|
6-8
|
1
|
|
|
|
Sheath roof/blkout
|
6-8
|
1
|
|
Finish Framing
|
Week # 6
|
Build stairs
|
2-4
|
1/2
|
|
|
March 31
|
Building wrap
|
4
|
1/2
|
|
|
|
Insulate tub wall
|
1
|
1/2
|
|
|
|
Pack window gaps
|
2
|
1/2
|
|
|
|
Set windows/doors
|
4-6
|
1/2
|
|
Roofing
|
Week # 7
|
|
|
|
|
|
April 2
|
Install soffit/fascia
|
6-8
|
1
|
|
|
April 5
|
Install flashings and shingles
|
6-8
|
1
|
|
Siding
|
Week # 8
|
|
|
|
|
|
April 14
|
Install siding
|
8-12
|
3
|
|
Exterior Paint
|
Week # 9
|
|
|
|
|
|
April 21
|
Finish siding & prep for paint
|
8-12
|
1
|
|
|
|
|
|
|
|
Building System
|
Week Needed
|
Task
|
Workers Needed
|
Days Allotted
|
|
|
Week # 10
|
|
|
|
|
|
April 28
|
Exterior paint
|
12
|
1-2
|
|
Plumbing
|
|
Rough-in
|
Sub-contracted
|
2
|
|
HVAC
|
|
Rough-in
|
Sub-contracted
|
2
|
|
Electrical
|
|
Rough-in
|
Sub-contracted
|
3
|
|
Inspections
|
|
Rough-ins
|
Building & Safety
|
1
|
|
Insulation
|
Week # 12
|
|
|
|
|
|
May 8
|
Install wall/rim joist insulation
|
6-12
|
1
|
|
Drywall
|
|
Hang drywall
|
6-12
|
3
|
|
|
Week # 13
|
|
|
|
|
|
May 15
|
Finish drywall
|
2-3
|
7
|
|
|
|
Tape and finish two coats
|
1-2
|
4
|
|
|
|
Texture/splatter coat
|
1-2
|
1
|
|
Exterior Finish
|
|
Finish Entries
|
6-8
|
2
|
|
Interior Finish
|
Week # 15
|
|
|
|
|
|
June 2
|
Prime Walls
|
8-10
|
1/2
|
|
|
|
Paint Walls
|
8-10
|
1/2
|
|
|
|
Underlayment
|
Sub-contracted
|
1
|
|
Trim
|
Week # 16
|
|
|
|
|
|
June 8
|
Set Cabinets
|
2-4
|
2
|
|
|
|
Install closet shelves
|
2-6
|
1
|
|
|
|
Trim windows/doors
|
2-6
|
2
|
|
|
Week # 17
|
|
|
|
|
|
June 12
|
Run Baseboard
|
2-6
|
2
|
|
|
|
Trim Stairs
|
2
|
1
|
|
|
|
Install Countertops
|
Sub-contracted
|
1
|
|
|
|
Install Hardware
|
2
|
1/2
|
|
Trades Finish
|
Week # 18
|
|
|
|
|
Electrical
|
June 19
|
Finish Electrical
|
Sub-contracted
|
1
|
|
Plumbing
|
|
Finish Plumbing
|
Sub-contracted
|
1
|
|
HVAC
|
|
Finish HVAC
|
Sub-contracted
|
1
|
|
|
|
Install Gutters
|
Sub-contracted
|
1
|
|
|
|
Install Flooring
|
Sub-contracted
|
2
|
|
|
Week # 19
|
|
|
|
|
|
June 26
|
Install Appliances
|
2-4
|
1/2
|
|
|
|
Final Grading
|
Sub-contracted
|
1
|
|
|
|
Seed
|
2-4
|
1
|
|
|
|
Final site clean-up
|
4-6
|
1/2
|
|
|
|
Affix Address
|
1
|
1/2
|
|
|
Week # 19
|
|
|
|
|
Final
City Inspection
|
June 28
|
Certificate of Occupancy Sign-off
|
Building & Safety
|
1
|
|
Punch-list Inspection
|
June 28
|
L/LCHFH
Site Supervisor
|
1
|
1/2
|
|
Punch-list remedies
|
June 28 - 30
|
Punch List -
As required
|
2-4
|
1
|
|
Dedication
|
July 14
|
Home Dedication
|
All Volunteers
|
1/2
|
|
|
|
|
|
|
|
|